INTRODUCTION
SERVICE DESCRIPTION
Application For Approval To Develop The Site
After an IPA has been attained, applicants then prepare and apply for the full detailed approval to develop the site. This application must be received and approved by the appropriate authorities prior to the commencement of any:
– Building, rebuilding, extending or altering the outside of any building;
– Forming or widening of any road or access;
– Earthworks altering the level of the land;
– Destruction of significant vegetation;
– Materially different use of land or building.
– Applicants wanting to carry out building work also need to apply for a Building Permit, to endorse the methods of construction as safe and adequate.
The City Council and DTCP will work closely with the Department of Waterways (Drainage connections) and Fiji Roads Authority as part of this approval. At the same time, DTCP will process the engineering plans (Step 4) of the new development.
Concurrently, applicants must also request for:
– Environment Impact Assessment (Step 2)
– New water and wastewater connections (Step 3) to the site.
The list of building standards highlights the mandatory and other standards which are required in all buildings in Fiji. All owners and developers are recommended to adhere to the standards (Download).
Potential Users: Owner of Land, Architect, Draftsman, Consulting Engineers
Submission Form(s)
– Application for Permission to Build (Download)
– Application for Development Permission (Download)
Checklists
– Checklist within application forms
– Major Development (Download)
– Minor Development (Download)
– Conditional Development (Download)
FAQs
– Department of Town and Country Planning (Download)
– Fiji Roads Authority (Download)
– Occupational Health and Safety Services (Download)
– National Fire Authority (Download)
SERVICE DETAILS
Service Availability
Monday – Thursday: 8:00am to 4:30pm
Friday: 8:00am to 4:00pm
Excluding weekends & public holidays
Turnaround Time
20 days*. Could be up to 3 mths depending on the scale of the development.
* Concurrent with Environment Impact Assessment (Step 2) and New Water and Wastewater Connection (Step 3)
Fee(s)
Calculated based on the value of works
Contacts
SCC Enquiry Counter
Email: customerservices@scc.org.fj
Tel: +679 3313433 Ext 305/306
Website: suvacity.org
DTCP Head of Development Control
Mr. Vinend Kumar
Email: dtcp@govnet.gov.fj
Tel: +679 3305 336
Fiji Roads Authority
Email: planning@fijiroads.org
Tel: +679 3100114
Website: www.fijiroads.org
Ministry of Waterways and Environment
Email: TBA
Tel: +679 3383155
You will be surprised, how easy we have made it for you to start or grow your business in Fiji.
Talk to us, we are ready to listen, and delighted to engage.
Level 2 and 3, Civic Tower, Victoria Parade, Suva
©2024 Ministry of Trade, Co-operatives, Micro, Small and Medium Enterprises, and Communications. All Rights Reserved
©2024 Ministry of Trade, Co-operatives, Small and Medium Enterprises, and Communications.
All Rights Reserved
Fiji Integrated Licenses and Permits Application System